Trench Surface limits

Good morning or afternoon.

Completed:
Pipe Networks
Pipe Templates
Pipe Runs (all I5 " RCP)

Question :
The pipe network is a mix of new and ex pipe, inlets, etc.

When applying template, it will running the full length the network, new and ex.

Can a length limitation be placed on the template to a specific stop, without having to divide into multiple smaller networks? (See image below)

The example below, the template should run from the first inlet west to the manhole.

Thank you.
-Jason

You’ll have to divide it into separate runs to limit where the surface is built.

I think you can also create a blank trench template and put that where you want the surface to stop, but not 100% sure on that.

Thank you for the information. I will try the blank template on monday.

Each template has a start location - it will start at the station you tell it to start and stop at either the end or the next twmplate you define. A run can have any number of Templates. To stop a template create a new template where you want the template to stop and dont add any template details ie a null Trmplate.

If you want to skip a zone eg feom station 200 to 275 then place a null template at 200 and a full template at 275

Alan