GCS900 Sync Rules are as follows
Office to TCC (Office Synchronizer)
Site Data including Avoidance Zones and Site Maps will upload to TCC
Design Data including Surfaces and Linework will upload to TCC
Coordinate System Data will upload to TCC
These files will all be transferred down to the machine on synchronization from the machine. Note if a Design is deleted on the machine it will not be re downloaded from TCC as it is marked as Deleted.
Device to TCC
Tag Production Files will upload to TCC
Point Recording Files will upload to TCC
MCH and DSP files will upload to TCC
LOG files will upload to TCC
TCC to Office (Office Synchronizer)
Point Recording Files will download to the Office
Sync Log Files will be downloaded to the office
TAG Files and Log Files will stop at TCC and not be downloaded to the office